Bond issues at a glance
Published 12:00 am Friday, July 11, 2008
The $25 million that the parish will receive from the 2008 bond issue will be broken down into six specific categories:
$4 million for hurricane levees
– Local match for phase I of the lakefront levee in St. John
$5 million for parish buildings
Improvements to the Edgard courthouse
Proposed government complex expansion on the east bank
$5 million for water treatment
Expansion of the Lyons Water Treatment Plant
Construction of a water tower
$3 million for roads
Woodland Drive extension
Miscellaneous road projects throughout the parish
$2.5 million for recreational facilities
– Construction of a parish gym with recreation department offices
$5 million for drainage
Canal improvements
Flooding concerns in Old Riverlands and Reserve